Westlake Pump Station Upgrades

Print
          

Three Week Project Timeline (posted 2/16/2017)

(Updated September 28, 2016) 

The new emergence generator for the pump station being hoisted into position

 

 

 

 

 



 

 

 

The new emergency generator for the pump station being hoisted into position.

 

 

 

 

 

 The generator’s protective housing being lowered into place

 

 

 

 

 

 

 

 

 

 

 

The generator’s protective housing being lowered into place.

 

New Electrical Pump in place(Updated September 12, 2016)

Electricians continue to install the complex wiring systems for the new pumps.

Two of the new electric pumps are in place; more will follow.

 

 

 

 

 

(Updated August 3, 2016)  

Westlake-Pump-Station-Upgrade_08.03.2016Electrician has begun installing protective conduits for the new power and control systems at the pump station. When complete, all conduits will be buried.

 

 

 

 

 

 

(Updated July 27, 2016)  

Concrete was poured to form the base for the backup generator.

Westlake Pump Station Upgrade_July2016

 

(Updated July 25, 2016) 

On Wednesday, July 27,  concrete will be delivered to the pump station site, beginning at 9 a.m. It is anticipated that up to four deliveries will be made to pour the foundation for the new backup generator.

(Updated July 20, 2016)

Work is underway installing electrical conduits for the new pumps and the building’s upgraded lighting system.  

In the coming weeks, approximately five concrete deliveries are expected for the base of the emergency generator.

Removal of an old internal compustion engine.(Updated July 6, 2016)

On Thursday, July 7, a crane will again be at the pump station work site to lift the propane tank away from its pad. In addition, the old concrete pad is scheduled to be demolished on Thursday, July 7 and Friday, July 8. Some noise and construction traffic should be expected in the Three Springs Park area during these activities. 

(Updated July 1, 2016)

Workers remove one of the old internal combustion engines from the Westlake Pump Station.  Electric motors will replace the engines.

(Updated June 30, 2016)

On Friday, July 1, a crane is scheduled to lift two pumps  out of the pump station building and move the propane tank off its foundation. The crane will be visible from Three Springs Park.

 

(Updated June 16, 2016)

Upgrade work has commenced at the Pump Station including the removal of old equipment and site preparation for the installation of new support infrastructure.

Westlake Pump Station Upgrades

(Updated June 6, 2016)

This project is one of the final components in the District’s multi-year “Backbone Improvement Program,” an infrastructure improvement initiative designed to ensure reliable water service to the Districts’ customers through improved flow volumes and system capacity under normal and emergency operating conditions.

During the week of June 6, work will commence on upgrading the Westlake Pump Station adjacent to Three Springs Park in Westlake Village.

The first elements of the project will include placing an onsite construction management office and internal electrical work at the facility.

This extensive project will replace older equipment, some of it in use since the 1970s.

Included in the project will be new electrically-powered pumps, replacing older natural-gas powered units, building maintenance and upgrades and the installation of a backup generator.

 


Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer

Navigation

View Full Site