Jed Smith Pipeline Replacement Project

Print
Press Enter to show all options, press Tab go to next option

Under Construction

Jed Smith Pipeline Replacement Project
Hidden Hills

Replacement of pipeline to improve reliable water delivery.

April 20, 2017

Crews have installed new pipe from Round Meadow to Jim Bridger and are continuing to trench and install towards Lewis and Clark Rd. They are base paving the trench behind their work area and will perform the final cap pave once the installation and all of the services/connections are complete. 

The project is currently currently on-track with the original schedule (see April 10, 2017 below).           

 Jed Smith Pipeline Replacement - 2017

 Jed Smith Pipeline Replacement - 2017

April 10, 2017

Read the project schedule (PDF).

Schedule subject to change due to weather or other considerations.

March 30, 2017

This project will take approximately 90-days begins Wednesday, April 5, 2017, finishing by the end of June, 2017.


Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player QuickTime Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer

Navigation

View Full Site